1 Using a 7-Day Work Week

Some companies have 7-day work weeks. In addition, in some situations, you want to treat Saturday and Sunday as work days to make it easier to count days.

First you need to create a custom calendar. To do so click on File-Calendar. Then, click on New, enter a name (e.g., SevenDayWeek), select "Create a new Base Calendar", and click OK.

Next, you need to use the custom calendar. Open the project (if it isn't alread), click on File-Information, select the "General" tab, select the appropriate "Base Calendar", and click on Close.